Welcome to Clyde, Ohio!
City Seal  
City Seal About Clyde    
City Seal  
City Seal   Home
Middle
Fiser City Manager
             Paul H. Fiser
            City Manager
        pfiser@clydeohio.org
            222 N. Main St
          Clyde, Ohio 43410

             419-547-6898
Sharon S. Smith
Administrative Secretary
ssmith@clydeohio.org
222 N. Main St
Clyde, Ohio 43410

419-547-6898







 

The City of Clyde, as provided in the City Charter, is a Council-Manager Government. The Manager's duty is to execute the laws and administer the
government of the municipality. The Manager is the Chief Executive Officer of the City and is responsible to Council for the proper administration
of the Municipal Government.
 

City Manager's Update to Council July 21, 2015

Construction of the Hoeflich Ditch has reached the City Limits and is within eight hundred feet (800') of completion (upper end).  The concrete pipe and basins have been ordered for Phase I of the Midvale/Elmdale Storm Sewer that will be installed by the General Service Department.  Phase I will run from the upper end of the Hoeflich Ditch approximately five hundred feet (500') to the East and start providing much needed drainage relief to the area.  Phase 2 which will continue East to Elmdale will be designed and built next year.  

The resurfacing projects are starting to fall in place.  Gerkin Paving, who was awarded the Community Park project, has confirmed that they will start construction on July 29 (weather permitting) and they are expecting to be done in three (3) days.  M & B Paving, contractors on the street resurfacing project, informed us that we would discuss a paving schedule on August 3.    

The project schedule for bidding of the Waste Water Treatment Plant Flow Equalization Basin has been finalized.  The project will be advertised on August 5, August 12 and August 19.  A Pre-Bid Meeting is set for August 13 at 10:00 a.m. in the Conference Room.  Bids will be opened at 10:00 a.m., August 27 also in the Conference Room.

The Environmental Service Department (EVSD) has begun some site work for the George Street Water Line Project.  This project, encompassing the area from US RT 20 to the railroad was budgeted for this year and will be completed in-house by the EVSD.  This part of George Street has had low pressure/low flow issues for years. 

Schreiber LLC, manufacturer of the two (2) new 24" Screw Pumps confirmed today that both pumps will be shipped this Friday and arrive at the Wastewater Treatment Plant on Monday.  We have notified Mosser Construction of the arrival date and are working to establish an earlier installation.  The installation will need to be coordinated with weather forecasts but we do have redundancy in the system in the form of other available pumps. 

Is everyone tired of mowing yet?  I believe the only person in the City of Clyde who has actually enjoyed this summer is Phil Farrar, Superintendent of the Water Treatment Plant (WTP).  Yesterday afternoon the WTP topped off both reservoirs and we are completely full.  That gives us almost 880 million gallons of raw water in storage or approximately seven hundred (700) days of usage at our current consumption rates.

As mentioned earlier, the deadline for our Ohio Public Works Applications is September 4, 2015.  We will be proposing our 2016 Street Construction/Resurfacing Program for funding.  The program includes approximately ten thousand feet (10,000') of roadway at an estimated cost of $300,000.           

We will be bringing legislation before council on August 5, consenting to the assignment of a Solar Power Purchase Agreement and related Solar Licensing Agreement.  

The July 28th Council Work Session will be dedicated to discussions on a proposed smoking ban  in the Clyde Parks.

Municipal Building | 222 North M

Municipal Building | 222 North Main Street | Clyde, Ohio 43410 |  City of Clyde, Ohio