Welcome to Clyde, Ohio!
City Seal  
City Seal About Clyde    
City Seal  
City Seal   Home
Fiser City Manager
             Paul H. Fiser
            City Manager
            222 N. Main St
          Clyde, Ohio 43410

Sharon S. Smith
Administrative Secretary
222 N. Main St
Clyde, Ohio 43410


The City of Clyde, as provided in the City Charter, is a Council-Manager Government. The Manager's duty is to execute the laws and administer the government of the municipality. The Manager is the Chief Executive Officer of the City and is responsible to Council for the proper administration of the Municipal Government. 

City Manager's Update to Council September 15, 2015

Site work at the Solar Field has begun.  Brush on the West side of the field has now been removed and final grading of the area will be completed over the next two weeks.  AEP and the city are currently working on a Press Release and the details for the Official Ground Breaking Ceremony on October 2, 2015.  That Ceremony will be held at the Solar Field at 10am. 

Clyde Light and Power has been working on the Solar Interconnection and that work is going smoothly.  The poles have been set, cross arms connected and the conductors are being hung this week.  We are awaiting some final equipment specifications from our electrical engineer and then will order our switches, capacitors and cabinets. 

The Ohio Publics Works (OPW), Sandusky County Sub-Committee will meet this Thursday morning at the County Engineer's Office to score all of the local applications and issue any county priority points before submittals are made to the State.  Our 2016 Paving Program, which was submitted, has a very strong preliminary score.  If we are able to negotiate enough priority points on Thursday, we should be in the funding range.  As I have mentioned in the past, these projects are peer reviewed and extremely competitive.  If funded, we will be receiving $175,000 from OPW.

The Waste Water Treatment Plant (WWTP) has completed the Annual Preventative Maintenance (APM) on Oxidation Ditch No.2 (ODIC2).  The work went well and  ODIC2 is back on-line.  The plant is now preparing to drain ODIC1, perform its APM and have it back on line prior to the start of the Equalization (EQ) Basin construction. 

While on the topic of the EQ Basin, we will be submitting the DEFA Water Pollution Control Loan Fund Agreement, yet this week.  Once that agreement is finalized, we will proceed with the execution of the construction contract with the Adena Corporation, out of Mansfield, Ohio.  The first loan payment will not be made until January 1, 2017.

The Environmental Service Department has the main line installed on George Street and the installation passed the pressure test.  Once the bacterial testing is complete, they will start hooking up services to the new 8" water line.  They have currently pulled off the job site to prepare for the upcoming fair. 

Speaking of the fair, it is hard to believe that it is that time of year again.  City crews started working on fair set-up last week and it will continue this week until everything is hooked-up and ready for the "soft opening" on Thursday evening.  The weather forecast is currently a little sketchy so let us hope it improves as the week progresses.  As always, Clyde will be ready for another successful fair so come on out and enjoy some "community spirit", have some great food, and enjoy the weekend. 

Municipal Building | 222 North M

Municipal Building | 222 North Main Street | Clyde, Ohio 43410 |  City of Clyde, Ohio